[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110885":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1110885,786,1,"单选题","在工程管理曲线中，当实际支付线低于计划线时，表明（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","进度延误",true,{"key":16,"text":17,"correct":18},"B","进度提前",false,{"key":20,"text":21,"correct":18},"C","成本节约",{"key":23,"text":24,"correct":18},"D","成本超支","2020版教材P200 一般在图上标注有一条 计划曲线和实际支付曲线，实际支付线高于计划线则实际进度快于计划，否则慢；",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]