[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110883":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1110883,786,1,"单选题","工程进度计划中以时间为横轴，以累计完成的工程费用的百分数为纵轴的图表化曲线称为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","横道图",false,{"key":16,"text":17,"correct":14},"B","斜率图",{"key":19,"text":20,"correct":14},"C","网络图",{"key":22,"text":23,"correct":24},"D","“S”曲线",true,"2020版教材P200 工程管理曲线线形像“S”形，故将工程管理曲线称为“S”曲线。“S”曲线是以时间为横轴，以累计完成的工程费用的百分数为纵轴的图表化曲线。一般在图上标注有一条计划曲线和实际支付曲线，实际支付曲线高于计划曲线则实际进度快于计划，否则慢；曲线本身的斜率也反映进度推进的快慢。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]