[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110882":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1110882,786,1,"单选题","路面工程施工中，相邻结构层之间的速度决定了相邻结构层之间的搭接类型，前道工序的速度快于后道工序时选用（ ）搭接类型。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","开始到开始",true,{"key":16,"text":17,"correct":18},"B","开始到完成",false,{"key":20,"text":21,"correct":18},"C","完成到开始",{"key":23,"text":24,"correct":18},"D","完成到完成","2020版教材P202 相邻结构层之间的速度决定了相邻结构层之间的搭接类型，前道工序的速度快于后道工序时选用开始到开始搭接类型，否则选用完成到完成搭接类型。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]