[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110880":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1110880,786,1,"单选题","在选择路面各结构层之间搭接类型时，后道工序快于前道工序时，应选择（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","STS",false,{"key":16,"text":17,"correct":14},"B","STF",{"key":19,"text":20,"correct":14},"C","FTS",{"key":22,"text":23,"correct":24},"D","FTF",true,"2020版教材P202 2. 相邻结构层之间的速度决定了相邻结构层之间的搭接类型， 前道工序的速度快于后道工序时选用开始到开始搭接类型，否则选用完成到完成搭接类型。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]