[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110877":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1110877,786,1,"单选题","S曲线是以时间为横轴，以（ ）为纵轴的图表曲线。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","各分部工程",false,{"key":16,"text":17,"correct":14},"B","工作内容",{"key":19,"text":20,"correct":14},"C","工程位置",{"key":22,"text":23,"correct":24},"D","累计完成的工程费用的百分数",true,"2020版教材P200 “S”曲线是以时间为横轴，以累计完成的工程费用的百分数为纵轴的图表化曲线。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]