[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110873":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1110873,786,1,"单选题","以下不属于施工总体部署内容的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建立施工管理机构",false,{"key":16,"text":17,"correct":14},"B","施工任务划分",{"key":19,"text":20,"correct":14},"C","施工顺序安排",{"key":22,"text":23,"correct":24},"D","施工总平面图设计",true,"2020版教材P194 施工总体部署内容：建立施工管理机构、施工任务划分、施工顺序。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]