[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110870":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1110870,786,1,"单选题","（ ）是施工组织设计的重要组成部分，是编制各项资源需求和进场计划的依据。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工总体部署",false,{"key":16,"text":17,"correct":14},"B","施工总平面布置图",{"key":19,"text":20,"correct":21},"C","施工进度计划",true,{"key":23,"text":24,"correct":14},"D","材料运输计划","2020版教材P194 根据已确定的施工进度计划，编制各项资源需求及进场计划。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]