[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110867":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1110867,786,1,"单选题","在施工组织设计时，施工进度计划一般在（ ）之后编制。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","季节性施工技术措施",false,{"key":16,"text":17,"correct":14},"B","主要分项工程施工工艺",{"key":19,"text":20,"correct":21},"C","主要工程项目的施工方案",true,{"key":23,"text":24,"correct":14},"D","安全管理与安全保证措施","2020版教材P193 一、施工组织设计的主要内容和编制方法： 1. 编制说明；2. 编制依据；3. 工程概况；4. 施工总体部署；5. 主要工程项目的施工方案；6. 施工进度计划。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]