[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110848":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1110848,786,1,"单选题","关于沥青混凝土拌和站场地建设要求的说法错误的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","沥青混凝土拌和站的占地面积在山岭重丘区不少于35000㎡",true,{"key":16,"text":17,"correct":18},"B","拌和站内宜设置工地试验室",false,{"key":20,"text":21,"correct":18},"C","拌和站的所有场地必须进行混凝土硬化处理",{"key":23,"text":24,"correct":18},"D","在场地外侧合适的位置设置沉砂井及污水过滤池，严禁将站内生产废水直接排放","2020版教材P302 该题主要考察的是沥青混凝土拌和站的场地建设。 拌和站应根据工程实际情况集中布置，宜采用封闭式管理。（新版教材已省略此处：拌和站内宜设置工地试验室。 表2B320111-7。沥青混凝土拌和站的占地面积在平原微丘区建设不少于3500㎡。在山岭重丘区，根据具体条件确定其占地面积。 水泥混凝土、路面面层储料应用混凝土进行硬化处理，路面基层储料场可用水温材料进行硬化处理。 施工污水处理达标后方可排入市政污水管网或河流。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]