[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110845":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1110845,786,1,"单选题","下列关于工程量清单的编写说法，错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","清单说明主要说明在编制工程量清单时应遵守的规定及注意事项",false,{"key":16,"text":17,"correct":14},"B","不同种类的工作应分别列出项目",{"key":19,"text":20,"correct":14},"C","同一性质但施工部位或条件不同的工作应分别列出项目",{"key":22,"text":23,"correct":24},"D","劳务和施工机械两个计日工表的计量（或计价）单位是“日”",true,"2020版教材P281 5. 计日工清单或专项暂定金额不可缺少 计日工清单是用来处理一些附加的或小型的变更工程计价的，清单中计日工的数量完 全是由业主虚拟的，用以避免承包人在投标时计日工的单价报得太离谱，有了计日工清单 会使合同管理很方便。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]