[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110843":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1110843,786,1,"单选题","某工程2016年签合同时，2016年相对于2013年的材料综合物价指数为110%，2017年相对于2013年的材料综合物价指数为132%。计算2017年1000万元材料费的实际结算价为（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1100",false,{"key":16,"text":17,"correct":18},"B","1200",true,{"key":20,"text":21,"correct":14},"C","1320",{"key":23,"text":24,"correct":14},"D","1420","2020版教材P289 该题主要考察的是工程价款价差调整的计算， 甲乙双方采用当时的预算（或概算）定额单价计算承包合同价，待竣工时，根据合理的工期及当地工程造价管理部门所公布的该月度（或季度）的工程造价指数，对原承包合同价予以调整。1000×132%\u002F110%=1200",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]