[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110842":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1110842,786,1,"单选题","工程款价差调整的主要方法不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程造价指数调整法",false,{"key":16,"text":17,"correct":14},"B","调值公式法",{"key":19,"text":20,"correct":14},"C","调价文件计算法",{"key":22,"text":23,"correct":24},"D","预计价格调整法",true,"2020版教材P289 这是考察工程价款价差调整的主要方法的知识点。工程价款价差调整主要有以下几种方法： （1）工程造价指数调整法； （2）实际价格调整法； （3）调价文件计算法； （4）调值公式法。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]