[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110833":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1110833,786,1,"单选题","工程项目成本计划应在（ ）的组织和主持下。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","公司总经济师",false,{"key":16,"text":17,"correct":14},"B","公司造价师",{"key":19,"text":20,"correct":21},"C","项目经理",true,{"key":23,"text":24,"correct":14},"D","项目造价师","2020版教材P268 工程项目施工成本计划应在项目经理的组织和主持下，根据合同文件、 企业下达的责 任目标成本、 企业施工定额、经优化选择的施工方案以及生产要素成本预测信息等进行编 制。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]