[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110827":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1110827,786,1,"单选题","变更工程的单价原则，其一是（ ），其二是公平合理原则。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人最终确定原则",false,{"key":16,"text":17,"correct":18},"B","约定优先原则",true,{"key":20,"text":21,"correct":14},"C","监理工程师审批原则",{"key":23,"text":24,"correct":14},"D","协商一致原则","2020版教材P264 该题主要考察的是变更的估价原则，根据《公路工程标准施工招标文件》的有关规定，变更工程应根据其完成的数量及相应的单价来办理结算。其中，变更工程的单价原则，其一是约定优先原则，其二是公平合理原则。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]