[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110826":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1110826,786,1,"单选题","施工中，监理工程师在收到承包人书面建议后，应与发包人共同研究，确认存在变更的，应在收到承包人书面建议后的（ ）天内作出变更指示。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","10",false,{"key":16,"text":17,"correct":18},"B","14",true,{"key":20,"text":21,"correct":14},"C","16",{"key":23,"text":24,"correct":14},"D","20","2020版教材P262 该题主要考察的是变更程序， 监理工程师在收到承包人书面建议后，应与发包人共同研究，确认存在变更的，应在收到承包人书面建议后的1 4天内做出变更指示。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]