[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110818":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1110818,786,1,"单选题","引起承包人索赔的因素众多，不是承包人索赔因素是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","赶工",false,{"key":16,"text":17,"correct":14},"B","开工受阻",{"key":19,"text":20,"correct":14},"C","气候影响",{"key":22,"text":23,"correct":24},"D","施工机械故障的停工",true,"2020版教材P264 在分析引起索赔的众多因素中，比较普遍的因素是赶工、开工受阻、 气候影 响、 工程量的增减、合同条款中与索赔密切相关的工程变更、增加工程及工程进度变化引 起的工期与费用的索赔。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]