[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110814":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1110814,786,1,"单选题","下列悬臂浇筑施工风险控制措施错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","挂篮加工完成后应先进行试拼",false,{"key":16,"text":17,"correct":14},"B","挂篮拼装时应两边对称进行",{"key":19,"text":20,"correct":14},"C","浇筑墩顶段（0号段）混凝土前应对托架模板进行检验和预压",{"key":22,"text":23,"correct":24},"D","预压的目的是消除杆件弹性变形和地基沉降",true,"2020版教材P249 2. 挂篮加工完成后应先进行试拼；挂篮正式拼装应在起步长度梁段（墩顶段或〇号 段） 混凝土达到要求的强度后才能进行，拼装时应两边对称进行。3. 浇筑墩顶段 号段） 混凝土前，应对托架、模板进行检验和预压， 消除杆件连接 缝隙、地基沉降和其他非弹性变形。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]