[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110813":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1110813,786,1,"单选题","下列翻模法施工风险防控措施错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","高墩翻模施工应编制专项施工方案并组织专家论证",false,{"key":16,"text":17,"correct":14},"B","翻模强度刚度及稳定性应满足要求",{"key":19,"text":20,"correct":14},"C","翻模施工时使用起重设备应经检测合格安全装置齐全有效",{"key":22,"text":23,"correct":24},"D","高墩施工人员上下须使用一字形爬梯",true,"2020版教材P248 （1）高墩翻模施工应编制专项施工方案，并组织专家论证。2） 翻模强度、刚度及稳定性应满足要求，模板安装前应组织相关人员验收和试拼 装，模板及其支架应采取有效的防倾覆临时固定措施。 混凝土强度达到设计要求后方可拆 模及进行模板翻转（3）翻模施工时使用起重设备，应经检测合格， 安全装置齐全、有效，起重设备操 作人员应持证上岗，严格按照操作规程作业。（7）高墩施工人员上下必须使用之字形爬梯， 安全网、防护栏等防护设施应安全 可靠。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]