[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110806":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1110806,786,1,"单选题","下列隧道工程洞口失稳控制措施中错误的开挖控制措施是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","控制开挖量等减少围岩扰动",false,{"key":16,"text":17,"correct":18},"B","采用台阶开挖时第一步开挖的台阶高度不宜超过1\u002F4的开挖高度",true,{"key":20,"text":21,"correct":14},"C","临时支护拆除后，及时施作二次衬砌",{"key":23,"text":24,"correct":14},"D","超前支护应及时到位，中间围岩开挖后及时封闭初期支护","2020版教材P251 洞口失稳控制措施（表2B320054-1）第一步开挖的台阶髙度不宜超过1\u002F3的开挖髙度",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]