[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110796":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1110796,786,1,"单选题","在后张法预应力筋的加工和张拉中，张拉伸长率需控制在（ ） 范围内。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","十4%",false,{"key":16,"text":17,"correct":14},"B","土5%",{"key":19,"text":20,"correct":21},"C","土6%",true,{"key":23,"text":24,"correct":14},"D","士8%","2020版教材P119 预应力筋采用应力控制方法张拉时，应以伸长值进行校核，实际伸长值与理论伸长值的差值应符合设计要求，设计无规定时，实际伸长值与理论伸长值的差值应控制在6%以内，否则应暂停张拉，待査明原因并采取措施予以调整后，方可继续张拉。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]