[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110779":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1110779,786,1,"单选题","在连续梁桥支架施工过程中，主要应注意控制（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","支架基础",false,{"key":16,"text":17,"correct":14},"B","拱架加载",{"key":19,"text":20,"correct":14},"C","卸架工艺",{"key":22,"text":23,"correct":24},"D","支架沉降",true,"2020版教材P223 连续梁桥① 支架浇筑时：支架沉降量的控制。② 先简支后连续：后浇段工艺控制、体系转换工艺控制、后浇段收缩控制、临时支座安装与拆除控制。③ 预应力梁：张拉预应力钢筋及压浆控制。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]