[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110721":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1110721,786,1,"单选题","复合式衬砌隧道和喷锚衬砌隧道施工时的现场监控量测的必测项目是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","围岩体内位移（洞内设点）",false,{"key":16,"text":17,"correct":14},"B","围岩体内位移（地表设点）",{"key":19,"text":20,"correct":14},"C","围岩压力",{"key":22,"text":23,"correct":24},"D","洞内、外观察",true,"2020版教材P163 根据《公路隧道施工技术规范》JTGF60-2009规定，复合式衬砌隧道和喷锚衬砌隧道施工时必须进行的必测项目有洞内外观察、周边位移、拱顸下沉、地表下沉4个，其余的为选测项目。 围岩体内位移（洞内设点）、围岩体内位移（地表设点）和围岩压力均不在4个必测项目中 。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]