[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110704":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1110704,786,1,"单选题","适用于无水或浅水河滩，地形相对平坦，孔数较多的中型梁板安装的架设方法是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","自行式吊机架设法",false,{"key":16,"text":17,"correct":14},"B","简易型钢导梁架设法",{"key":19,"text":20,"correct":21},"C","跨墩龙门架架设法",true,{"key":23,"text":24,"correct":14},"D","联合架桥机架设法","2020版教材P136 （5） 跨墩龙门架架设法：预制梁由轨道平车或者平板拖车运至桥孔一侧，用两台同步运行的跨墩龙门吊将梁吊起再横移到设计位置落梁就位。适用条件：无水或浅水河滩，地形相对平坦，孔数较多的中型梁板安装。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]