[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110672":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1110672,786,1,"单选题","明挖扩大基础施工中，黏性土在半干硬或硬塑状态，基坑顶无活荷载，稍松土质，基坑深度不超过0．5m时，可采用（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","垂直坑壁基坑",true,{"key":16,"text":17,"correct":18},"B","阶梯型基坑",false,{"key":20,"text":21,"correct":18},"C","斜坡型基坑",{"key":23,"text":24,"correct":18},"D","混合型基坑","2020版教材P121 对于在干涸河滩、河沟中，或经改河、筑堤能排除地表水的河沟中，在地下水位低于基底，或渗透量少，不影响坑壁稳定以及基础埋置不深，施工期较短，挖基坑时，不影响临近建筑物安全的场所，可选用坑壁不加支撑的基坑。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]