[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110641":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1110641,786,1,"单选题","下列关于钢筋混凝土梁桥预拱度偏差的防治措施叙述有误的是（）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","加强施工控制，及时调整预拱度误差",false,{"key":16,"text":17,"correct":14},"B","控制预制梁与桥面系铺装的龄期差",{"key":19,"text":20,"correct":21},"C","预制梁存梁时间不宜过短",true,{"key":23,"text":24,"correct":14},"D","严格控制预应力筋在结构中的位置","2020版教材P155 该题主要考察的是钢筋混凝土梁桥预拱度偏差的防治措施 二、预拱度偏差防治措施（1）提高支架基础、支架及模板的施工质量，确保模板的标高无偏差；（2）加强施工控制，及时调整预拱度误差；（3）严格控制张拉时的混凝土强度，控制张拉的试块应与梁板同条件养护，对于预制梁还需控制混凝土的弹性模量；（4）要严格控制预应力筋在结构中的位置，波纹管的安装定位应准确；控制张拉时的应力值，按要求的时间持荷；（5）张拉千斤顶定期标定，钢绞线伸长值的计算应采用同批钢绞线弹性模量的实测值； 考前黑钻押题，金考典软件考前更新，下载链接 www.jinkaodian.com（6）预制梁存梁时间不宜过长，控制预制梁与桥面系铺装的龄期差。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]