[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110632":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1110632,786,1,"单选题","盖板涵（预制吊装）施工工序中，吊装盖板之前是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","浆砌墙身",false,{"key":16,"text":17,"correct":18},"B","现浇板座",true,{"key":20,"text":21,"correct":14},"C","出入口浆砌",{"key":23,"text":24,"correct":14},"D","防水层施工","2020版教材P151 盖板涵（预制吊装）施工工序： 测量防线→基坑开挖→下基础→浆砌墙身→现浇板座→吊装盖板→出入口浆砌→防水层施工→涵洞回填及加固。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]