[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110569":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1110569,786,1,"单选题","填隙碎石施工中，首次撒铺填隙料的紧前工序是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","初压",true,{"key":16,"text":17,"correct":18},"B","摊铺粗碎石",false,{"key":20,"text":21,"correct":18},"C","洒水饱和",{"key":23,"text":24,"correct":18},"D","碾压滚浆","2021\u002F2020版教材P47 填隙碎石的干法施工应符合下列规定：(1) 初压宜用两轮压路机碾压 3?4 遍，使集料稳定就位，初压结束时，表面应平整，并具有规定的路拱和纵坡。(2) 填隙料应采用石屑撒布机或类似的设备均匀地撒铺在已压稳的集料层上。松铺厚度宜为 25~30mm，必要时，可用人工或机械扫匀。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]