[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110563":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1110563,786,1,"单选题","在路拌法水泥稳定土基层施工中，四个工序编号为：①准备下承层；②拌和；③洒水闷料；④整形，正确的工序先后排列是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","①②③④",false,{"key":16,"text":17,"correct":14},"B","②①③④",{"key":19,"text":20,"correct":14},"C","①②④③",{"key":22,"text":23,"correct":24},"D","①③②④",true,"2021\u002F2020版教材P54 2B312012- 2混合料人工路拌法施工的工艺流程图：可以得出顺序为准备下承层-洒水、闷料-拌和-整形",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]