[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110525":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1110525,786,1,"单选题","路面内部排水施工时，渗入水在路面结构内的最大渗流时间，冰冻区不应超过（ ）h。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1",true,{"key":16,"text":17,"correct":18},"B","1.5",false,{"key":20,"text":21,"correct":18},"C","2",{"key":23,"text":24,"correct":18},"D","2.5","2021\u002F2020版教材P94 渗入水在路面结构最大渗流时间，冰冻区不应超过1h，其他地区不超过2h。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]