[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110522":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1110522,786,1,"单选题","SMA混合料的拌和时，采用颗粒状纤维，纤维应在粗细集料投料后立即加入，干拌时间较常规混合料生产（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","增加5～10s",true,{"key":16,"text":17,"correct":18},"B","减少5～10s",false,{"key":20,"text":21,"correct":18},"C","增加20～30s",{"key":23,"text":24,"correct":18},"D","减少20～30s","2021\u002F2020版教材P81 采用颗粒状纤维，纤维应在粗细集料投料后立即加入，干拌时间较常规混合料生产增加5-10s,",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]