[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110512":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1110512,786,1,"单选题","下列关于水泥混凝土路面施工的说法错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","模板与混凝土拌和物接触表面应涂隔离剂",false,{"key":16,"text":17,"correct":14},"B","模板拆除应在混凝土抗压强度不小于8.0MPa方可进行",{"key":19,"text":20,"correct":21},"C","摊铺前应对基层表面进行风干处理，不得润湿",true,{"key":23,"text":24,"correct":14},"D","混凝土运输过程中应防止漏浆和漏料","2021\u002F2020版教材P87 5.模板与混凝土拌和物接触表面应涂隔离剂。 6.模板拆除应在混凝土抗压强度不小于8.0MPa时方可进行。 3.混凝土运输过程中应防止漏浆、漏料和污染路面，途中不得随意耽搁。 2.准备工作 （1）摊铺段夹层或封层质量应检验合格，对于破损或缺失部位，应及时修复。表面应清扫干净并洒水润湿，并采取防止施工设备和机械碾坏封层的措施。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]