[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110474":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1110474,786,1,"单选题","当下卧地层平坦时，抛石挤淤法处理软基中，抛投顺序正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","顺里程方向平行抛填",false,{"key":16,"text":17,"correct":14},"B","先从路堤两边开始，向中部扩展",{"key":19,"text":20,"correct":21},"C","应沿道路中线向前呈三角形抛填，再渐次向两旁展开",true,{"key":23,"text":24,"correct":14},"D","应从低的一侧向高的一侧扩展","2021\u002F2020版教材P19 5. 抛石挤淤施工规定 （1） 当下卧地层平坦时，应沿道路中线向前呈三角形抛填，再渐次向两旁展开，将淤泥挤向两侧。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]