[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110473":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1110473,786,1,"单选题","关于抛石挤淤施工技术说法正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","在抛石高出水面后，应采用轻型机具碾压紧密，然后在其上设反滤层，再填土压实",false,{"key":16,"text":17,"correct":14},"B","当下卧地层具有明显横向坡度时，应从下卧层低的一侧向高的一侧扩展，并在高侧边部多抛投不少于2米宽，形成平台顶面",{"key":19,"text":20,"correct":14},"C","当下卧地层平坦时，应沿道路中线向前直线抛填，将淤泥挤向两侧",{"key":22,"text":23,"correct":24},"D","当下卧地层平坦时，应沿道路中线向前呈三角形抛填，再渐次向两旁展开，将淤泥挤向两侧",true,"2021\u002F2020版教材P19 当下卧地层平坦时，应沿道路中线向前呈三角形抛填，再渐次向两旁展开，将淤泥挤向两侧 当下卧地层具有明显横向坡度时，应从下卧层高的一侧向低的一侧扩展，并在低侧边部多抛投不少于2米宽，形成平台顶面 在抛石高出水面后，应采用重型机具碾压紧密，然后在其上设反滤层，再填土压实",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]