[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110462":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1110462,786,1,"单选题","塑料排水板的施工工艺程序中，摊铺上层砂垫层的前一个工序是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","拔出套管",false,{"key":16,"text":17,"correct":14},"B","割断塑料排水板",{"key":19,"text":20,"correct":14},"C","塑料排水板穿靴",{"key":22,"text":23,"correct":24},"D","机具移位",true,"2021\u002F2020版教材P21 塑料排水板的施工工艺程序为：整平原地面→摊铺下层砂垫层→机具就位→塑料排水板穿靴→插入套管→拔出套管→割断塑料排水板→机具移位→摊铺上层砂垫层。摊铺上层砂垫层是最后一个工序，机具不移开就无法摊铺上层砂垫层，拔出套管、割断塑料排水板、塑料排水板穿靴均在机具移位之前完成",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]