[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110429":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1110429,786,1,"单选题","土方填筑分几个作业段施工时，接头部位如不能交替填筑，则对先填路段的正确处理方式是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","应进行支挡",false,{"key":16,"text":17,"correct":18},"B","应按1∶1坡度分层留台阶",true,{"key":20,"text":21,"correct":14},"C","应设置锥坡",{"key":23,"text":24,"correct":14},"D","停工等待","2021\u002F2020版教材P7 填方分几个作业段施工时，接头部位如不能交替填筑，则先填路段，应按1∶1坡度分层留台阶；如能交替填筑，则应分层相互交替搭接，搭接长度不小于2m。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]