[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110427":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1110427,786,1,"单选题","当由于地形限制或填筑堤身较高，不宜采用另外两种方法施工时，施工方法宜采用（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","水平分层填筑法",false,{"key":16,"text":17,"correct":14},"B","纵向分层填筑法",{"key":19,"text":20,"correct":14},"C","竖向填筑法",{"key":22,"text":23,"correct":24},"D","混合填筑法",true,"2021\u002F2020版教材P8 混合填筑法适用于因地形限制或填筑堤身较高，不宜采用水平分层法或竖向填筑法自始至终进行填筑的情况。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]