[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110417":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1110417,786,1,"单选题","关于水泥混凝土空心块护坡施工的说法，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","预制块应与坡面紧贴，不得有空隙，并与相邻坡面平顺",false,{"key":16,"text":17,"correct":18},"B","预制块铺置应在路堤填筑工程中施工",true,{"key":20,"text":21,"correct":14},"C","预制块经验收合格后方可使用",{"key":23,"text":24,"correct":14},"D","预制块铺置前应将坡面整平","2021\u002F2020版教材P30 （1）预制块铺置应在路堤沉降稳定后方可施工。 （2）预制块铺置前应将坡面整平。 （3）预制块经验收合格后方可使用。 （4）预制块应与坡面紧贴，不得有空隙，并与相邻坡面平顺。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]