[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110397":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1110397,786,1,"单选题","路基边坡病害的原因不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","路基填筑层有效宽度不够，边坡二期贴补",false,{"key":16,"text":17,"correct":18},"B","暗涵结构物基底沉降或涵背回填压实度不符合规定",true,{"key":20,"text":21,"correct":14},"C","路基基底存在软土且厚度不均",{"key":23,"text":24,"correct":14},"D","路基处于陡峭的斜坡面上，原地面未开挖反坡台阶","2021\u002F2020版教材P43 路基边坡病害的防治。 一、 原因分析： 1. 设计对地震、洪水和水位变化影响考虑不充分； 2.路基基底存在软土且厚度不均； 3.换填土时清淤不彻底； 4.填土速率过快，施工沉降观测、侧向位移观测不及时； 5.路基填筑层有效宽度不够，边坡二期贴补； 6.路基顶面排水不畅； 7.纵坡大于12%的路段未采用纵向水平分层法分层填筑施工； 8.用透水性较差的填料填筑路堤处理不当； 9.边坡植被不良； 10.未处理好填挖交界面； 11.路基处于陡峭的斜坡面上。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]