[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110352":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1110352,786,1,"单选题","在连续梁桥支架施工过程中，主要应注意控制（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","支架基础",false,{"key":16,"text":17,"correct":14},"B","拱架加载",{"key":19,"text":20,"correct":14},"C","卸架工艺",{"key":22,"text":23,"correct":24},"D","支架沉降",true,"本题考查的是公路工程质量控制方法及措施。在连续梁桥支架施工过程中，主要应注意控制支架沉降量。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]