[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110350":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1110350,786,1,"单选题","下列关于洞口失稳的控制措施，错误的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","临时支护拆除后，及时施做二次衬砌",false,{"key":16,"text":17,"correct":14},"B","加强第三方监控量测，做到及时预测预警",{"key":19,"text":20,"correct":21},"C","台阶开挖时，第一步开挖的台阶高度不宜超过1\u002F2的开挖高度",true,{"key":23,"text":24,"correct":14},"D","控制开挖量等，减少围岩扰动，超前支护应及时到位","本题考查的是隧道工程施工安全管理措施。台阶开挖时，第一步开挖的台阶高度不宜超过1\u002F3的开挖高度。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]