[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110348":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1110348,786,1,"单选题","工程变更通常实行分级审批管理制度，一般工程变更由（）签署工程变更令。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","驻地监理工程师",false,{"key":16,"text":17,"correct":18},"B","总监理工程师",true,{"key":20,"text":21,"correct":14},"C","业主",{"key":23,"text":24,"correct":14},"D","国家计划主管部门","本题考查的是施工阶段工程变更的管理。一般工程变更的审批程序：（1）工程变更的提出人向驻地监理工程师提出工程变更的申请；（2）驻地监理工程师对变更申请的可行性进行评估，并写出初步的审查意见；（3）总监理工程师对驻地监理工程师审查的变更申请进行进一步的审定，并签署审批意见。总监理工程师签署工程变更令。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]