[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110339":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1110339,786,1,"单选题","预应力锚固施工风险控制措施中错误的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","钻孔后要清孔，锚索入孔后24小时内注浆",true,{"key":16,"text":17,"correct":18},"B","采用二次注浆加大锚固力",false,{"key":20,"text":21,"correct":18},"C","脚手架高度在10～15m时，应设置一组（4～6根）缆风索",{"key":23,"text":24,"correct":18},"D","正式施工前应进行锚固力基本试验","本题考查的是路基工程施工安全管理措施。钻孔后要清孔，锚索入孔后1小时内注浆。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]