[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110335":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1110335,786,1,"单选题","下列关于工程量清单的说法错误的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","当图纸与工程量清单所列数量不一致时，应以清单所列数量作为报价的依据",false,{"key":16,"text":17,"correct":14},"B","不同种类的工作应分别列出项目",{"key":19,"text":20,"correct":14},"C","清单中没有填入价格的子目，承包人必须按指令完成",{"key":22,"text":23,"correct":24},"D","实际施工过程中，业主应按照清单价格和数量进行结算",true,"本题考查的是公路工程工程量清单计价的应用。因为在实际施工过程中，可能会因各种原因与设计条件不一致，从而产生工程量的数量变化，业主应按实际工程量支付工程费用。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]