[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110332":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1110332,786,1,"单选题","可以反映出关键工序和关键线路的公路工程进度计划形式是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","横道图",false,{"key":16,"text":17,"correct":14},"B","工程管理曲线",{"key":19,"text":20,"correct":14},"C","斜率图",{"key":22,"text":23,"correct":24},"D","网络图",true,"本题考查的是公路工程进度计划的编制特点。横道图—公路工程的进度横道图是以时间为横坐标，以各分部（项）工程或工作内容为纵坐标。“S”曲线—“S”曲线是以时间为横轴，以累计完成的工程费用的百分数为纵轴的图表化曲线。斜率图—斜率图是以时间（月份）为横轴，以累计完成的工程量的百分数为纵轴。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]