[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110331":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1110331,786,1,"单选题","一般网络图（无时标）进度检查的割线法称为（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","香蕉曲线比较法",false,{"key":16,"text":17,"correct":14},"B","S曲线比较法",{"key":19,"text":20,"correct":21},"C","完工时点比较法",true,{"key":23,"text":24,"correct":14},"D","公路工程进度表","本题考查的是公路工程进度控制与管理。用网络图来进行进度检查是进度控制中计划检查最简单和最有效的方法。在检查时需记载实际进度情况，收集进度的实际信息与实际进度前锋线方法相同。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]