[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110327":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1110327,786,1,"单选题","下面关于工程量计量表述错误的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","凡是超过图纸所示的任何长度、面积或体积，均不予计量",false,{"key":16,"text":17,"correct":18},"B","全部必需的模板、脚手架应单独计量",true,{"key":20,"text":21,"correct":14},"C","如果规范规定的分项工程未在工程细目中出现，则认为是其他相关工程的附属义务，不单独计量",{"key":23,"text":24,"correct":14},"D","所有计量证书必须由承包人和监理工程师共同签署才能作为支付的凭证","全部必需的模板、脚手架、装备、机具和联结螺栓、垫圈等其他材料，应包括在其他支付细目中，不单独计量。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]