[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110326":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1110326,786,1,"单选题","对于重要工程变更的程序中，说法正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","监理工程师可以直接下达工程指令",false,{"key":16,"text":17,"correct":18},"B","业主可以决定所有的工程变更",true,{"key":20,"text":21,"correct":14},"C","这部分工程是指工程造价影响较大，但是不需要业主批准的工作",{"key":23,"text":24,"correct":14},"D","对这些工程变更工作，业主在审批工程变更之前应事先取得国家计划主管部门的批准","重要工程变更的审批，是指对工程造价影响较大，需要业主批准的工程变更工作。其审批程序是：监理工程师在下达工程并更令之前，一是要报业主批准，二是要同承包人协商确定变更工程的价格不超过业主批准的范围。如果超过业主批准的总额，监理工程师应在下达工程并更令之前请求业主作进一步的批准或授权。D描述的是重大工程变更的审批程序。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]