[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110324":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1110324,786,1,"单选题","公路工程进度计划的主要形式中，既能反映各分部（项）工程的进度，又能反映工程总体进度的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","时标网络图",false,{"key":16,"text":17,"correct":18},"B","”S”曲线和横道图结合的公路工程进度表",true,{"key":20,"text":21,"correct":14},"C","单代号搭接网络图",{"key":23,"text":24,"correct":14},"D","”S”曲线","在公路工程中，常常将\"S\"曲线和横道图合并于同一张图表中，称之为\"公路工程进度表\"，既能反映各分部（项）工程的进度，又能反映工程总体的进度。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]