[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110314":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1110314,786,1,"单选题","对于围岩压力来得快、来得大，对围岩变形及地表下沉有严格限制要求的较弱破碎围岩隧道工程施工应采用（）预支护形式。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","超前锚杆",false,{"key":16,"text":17,"correct":14},"B","超前小导管注浆",{"key":19,"text":20,"correct":21},"C","管棚",true,{"key":23,"text":24,"correct":14},"D","插板","本题考查的是公路隧道超前支护。管棚主要适用于围岩压力来得快、来得大，用于对围岩变形及地表下沉有较严格限制要求的软弱破碎围岩隧道工程中。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]