[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110311":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1110311,786,1,"单选题","连拱隧道施工的顺序正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","贯通中导洞—中隔墙—主洞开挖",true,{"key":16,"text":17,"correct":18},"B","中隔墙—贯通中导洞—主洞开挖",false,{"key":20,"text":21,"correct":18},"C","主洞开挖—中隔墙—贯通中导洞",{"key":23,"text":24,"correct":18},"D","主洞开挖—贯通中导洞—中隔墙","本题考查的是公路小净距及连拱隧道施工。连拱隧道开挖宜先贯通中导洞、浇筑中隔墙，然后依次开挖主洞。中隔墙顶与中导洞初支间应用混凝土回填密实。主洞开挖时，左右两洞开挖掌子面错开距离宜大于30m。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]